Generator maintenance procedures on a regular basis


 (1) under normal circumstances,every 7 days to start the generator no-load commissioning maintenance load of commissioning.5 - lOmin,every time with every month (2) disconnect the output of the generator automatic switch,puts selector switch to manual.(3) check the battery level,not enough level should be equipped with the electrolyte or distilled water,check the liquid proportion,in soda solution soaking and wipe up,coated with vaseline,then tighten the screw connection,and test ac induction motor the battery,battery voltage,and battery charging current at ordinary times.(4) remove the air filter,clean with gas and dust,after the sun to dry.Check the oil oil,such as turbidity or bad generator generator set should be replaced.Diesel engine running after 250 hours,water,oil,diesel oil filter should be changed.

(5) in diesel filter,should check whether the oil valve and valve in full capacity,with or without a fixed screw loose then manual oil pump,eliminate the air in the oil.(6) to check the cooling water plane position at ordinary times,change the water tank in the cooling water,in water,should add rust water.Then the shaking motor winding insulation resistance measurement.(7) to check whether there is oil leakage,the entire unit ground are in good condition,and then do a good job in cleaning unit.(8) open the control cabinet,check the fuse,screw contacts are motor vehicle in good condition,and then close the power control and help keep the oil temperature,water temperature sensor reset,and manual commissioning,oil pressure,output voltage,frequency,etc.(9) manually run 20 ~ 30 minutes,to simulate a power outage of commissioning,and check the ventilation,fire control system whether normal operation.After downtime,place electricalmotor1.blogspot.com selection switch on auto parts,close the output switch.

没有评论:

发表评论